What does 'Acceptance testing' assess in PRINCE2 Agile?

Prepare effectively for the PRINCE2 Agile Foundation Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Acceptance testing in PRINCE2 Agile focuses on determining whether the project deliverables meet the established acceptance criteria. This testing is critical as it verifies that the outputs align with the client's requirements and expectations, which were defined at the outset of the project. By conducting acceptance tests, stakeholders can evaluate whether the project has delivered the expected value and functionality, ensuring that the final product is fit for purpose and ready for deployment.

This process involves collaboration between the project team and stakeholders to assess whether the developed features satisfy the agreed-upon conditions for success. It acts as a quality assurance step before final sign-off, allowing any issues to be addressed while there is still the opportunity to make adjustments.

In contrast, assessing the performance of the project team, funding allocation, or timeline accuracy can be part of other project management activities but do not directly relate to the acceptance of specific deliverables in PRINCE2 Agile.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy